Cloud provider building large AI data centers for OpenAI.

4 timelines · 34 dated entries · last update Oct 22, 2026 · JSON

Wikipediaoracle.com

Role in each timeline

Oracle across every timeline

Every dated entry that names Oracle, from all 4 timelines, newest first. Earlier years show only dates and titles; click a year to show the details.

202615 entries
202512 entries
  1. Dec 10, 2025Oracle reports $523 billion in remaining performance obligations
  2. Oct 16, 2025Oracle says it is raising its long-term financial outlook
  3. Oct 14, 2025Oracle plans a public 50,000-GPU MI450 supercluster
  4. Sep 23, 2025OpenAI, Oracle, and SoftBank announce five Stargate data-center sites
  5. Sep 9, 2025Oracle signs four multibillion-dollar contracts with three customers
  6. Sep 9, 2025Oracle reports $455 billion of remaining performance obligations, up 359 percent
  7. Jul 22, 2025OpenAI and Oracle agree to develop 4.5 GW of Stargate capacity
  8. Jun 12, 2025MI350 series rolling out at Oracle; Helios rack on MI400 previewed for 2026
  9. Jun 11, 2025Backlog reaches $138 billion at the close of fiscal 2025
  10. Mar 10, 2025Backlog reaches $130 billion
  11. Mar 10, 2025Oracle signs more than $48 billion of sales contracts in Q3
  12. Jan 21, 2025OpenAI names Oracle an initial Stargate equity funder
20246 entries
  1. Dec 9, 2024Backlog holds at $97 billion
  2. Dec 9, 2024Oracle reports 336% growth in quarterly GPU consumption
  3. Sep 26, 2024Fireworks AI adopts OCI bare-metal MI300X instances
  4. Sep 9, 2024Backlog reaches $99 billion as the AI contracts start landing
  5. Sep 9, 2024Oracle reports 162 cloud data centers operating or under construction
  6. Jun 11, 2024Oracle reports $98 billion in remaining performance obligations
20231 entry
  1. Dec 6, 2023MI300X and MI300A launched; Microsoft Azure, Oracle and the major OEMs line up