C.C. Wei
Chairman and CEO of TSMC.
Role in each timeline
- TSMC Arizona: From a $12 Billion Fab to a $265 Billion Gigafab Cluster
TSMC chairman and CEO who described the Arizona acceleration, capacity target, and US$265 billion expansion.
C.C. Wei across every timeline
Every dated entry that names C.C. Wei, from all 1 timeline, newest first.
20262 entries
- Another US$100 billion for Arizona: total reaches US$265 billion for more 2nm fabs and packaging Announcement
Alongside second-quarter 2026 results, chairman C.C. Wei said TSMC would invest an additional US$100 billion in Arizona to build several more wafer fabs for 2-nanometer and below technologies plus advanced packaging fabs, bringing the state total to US$265 billion. Wei said there was a plan but no firm schedule for the new sites.
on TSMC Arizona: From a $12 Billion Fab to a $265 Billion Gigafab Cluster - TSMC says it is pulling forward Arizona fab schedules toward an independent gigafab cluster Announcement
On the fourth-quarter 2025 call, TSMC said it was pulling forward existing fab schedules in Taiwan and Arizona, that Arizona yields and defect density were almost equal to Taiwan, and that the plan would scale an independent gigafab cluster in Arizona with around 30 percent of 2nm-and-more-advanced capacity.
on TSMC Arizona: From a $12 Billion Fab to a $265 Billion Gigafab Cluster
20252 entries
- Second fab construction complete, production pulled forward; 30% of 2nm-and-beyond capacity to be in Arizona Announcement
On the second-quarter 2025 call, CEO C.C. Wei said construction of the second Arizona fab, for 3nm, was complete and its volume production schedule was being sped up by several quarters. Work on the third fab, for 2nm and A16, had begun. Wei said about 30 percent of TSMC's 2nm-and-smaller capacity would eventually be in Arizona.
on TSMC Arizona: From a $12 Billion Fab to a $265 Billion Gigafab Cluster - TSMC adds US$100 billion for three more fabs, two packaging plants and an R&D center: US$165 billion total Announcement
Announced at the White House with President Trump, the expansion took TSMC's planned U.S. investment from US$65 billion to US$165 billion, covering three additional fabs, two advanced packaging facilities and a major R&D team center in Arizona.
on TSMC Arizona: From a $12 Billion Fab to a $265 Billion Gigafab Cluster
20241 entry
- First Arizona fab enters N4 engineering-wafer production Update
TSMC said its first Arizona fab entered engineering-wafer production in April using N4 process technology. The statement concerned engineering-wafer production.
on TSMC Arizona: From a $12 Billion Fab to a $265 Billion Gigafab Cluster
20211 entry
- TSMC begins construction at its Arizona fab site Update
TSMC said it had started construction at an Arizona site for a computer-chip factory. The company planned to spend US$12 billion on the facility.
on TSMC Arizona: From a $12 Billion Fab to a $265 Billion Gigafab Cluster